updated:February 28th, 2008| November 2001 | Master Plan Task Force established to develop a 20-year master plan |
| February 16, 2004 | Master Plan Task Force hires Todd and Associates as our Architect |
| July 19, 2004 | Final decision for General Contractor Rowland and Companies |
| September 13, 2004 | RSI approved as our Fundraiser consulting firm |
| August 8, 2005 | Kickoff Meeting with Todd and Associates on Initial Schematic Design phase |
| November, 2005 | Initial Breaking New Ground Team Meeting |
| Dec 12, 2005 | Re-zoning approved by City of Scottsdale |
| January, 2006 | Initial publication to congregation about BNG |
| Feb-April, 2006 | BNG Meetings for the congregation |
| April 1-2, 2006 | Celebration Weekend / 3-year financial commitments from congregation turned in |
| June 2006 | Schematic Design for Phase 1-3 begins |
| January 2007 | Design Development for Phase 1 begins |
| Februrary 8, 2007 | Master Plan submitted for Scottsdale Design and Review board |
| March 22, 2007 | DR Board Approval of Master Plan |
| April 2007 | Construction Documents begin |
| July 2007 | Submit Construction Docs for City Review for Permit |
| July - September 2007 | Additional Reviews and Corrections for Attaining Building Permit |
| End of August | received City comments on Construction Drawings after first review; revising drawings for second submittal |
| September 26, 2007 | Second submittal to the city of Scottsdale |
| Oct 14, 2007 | Congregational Vote re: financing for the project. |
| December 2007 | Building Permit Available |
| February 3, 2008 | Ground breaking ceremony - Move Worship Services and schedule to C-1 |
| February 2008 | Phase 1 Construction / Worship Center remodel begins |
Late November / December 2008 | Worship 1 Remodel complete |
| December 2008/January 2009 | Phase 1 complete !!! |